Historical Development

Historical Development

2018

Initiative from Aker Solutions to TESS at ONS and first meeting 3Q-18

2019

Concept study with workshop meetings and study report (TRL-1) 

   Demo day at Aker Solutions, Fornebu with Scale model (TRL-2) 

2020

Concept presentations and meetings with Aker BP and other O&G companies

2021

RFI and RFQ from Aker BP. Budgetary offer submitted for NOAKA. 

2022

Feasibility study, design and development of full-scale prototype. 

   Testing of Funnel and termination (TRL-3 and TRL-4)  

2023

Contract with Aker BP for delivery to Yggdrasil - Hugin A. 

2024

Product development and testing 

2025

System integration testing and delivery to client.  

   Assembly on Hugin A platform.

2026

Potential additional testing onshore/offshore. 

2027

System in operation as base case for chemical loading.